Subject: TW/ Lonestar Ward and Pecos Counties interconnect
 bi-directional--A-release
Cc: kimberly.watson@enron.com
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
Bcc: kimberly.watson@enron.com
X-From: Abdmoulaie, Mansoor </O=ENRON/OU=NA/CN=RECIPIENTS/CN=MABDMOU>
X-To: Lokay, Michelle </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Mlokay>
X-cc: Watson, Kimberly </O=ENRON/OU=NA/CN=RECIPIENTS/CN=Kwatson>
X-bcc: 
X-Folder: \Michelle_Lokay_Mar2002\Lokay, Michelle\Inbox
X-Origin: Lokay-M
X-FileName: mlokay (Non-Privileged).pst


The following is a level "A" cost estimate to make TW/ Lonestar existing interconnects bi-directional.


TW/ Lonestar at Ward County ( 50 to 60 mmcf/d)


According to Operations this is already bi-directional . The only things are required on this one is to take the flapper out of the check-valve 
and blow down the gas in 5.33 miles of 12".

Cost of gas loss& labor = $8,000




TW/ Lonestar at Pecos County ( 100 mmcf/d)

A): TW/ Lonestar interconnect


	Scope: On this one we need a bi-directional valve skid using the existing meter run.
	Cost of material& labor= $ 195,000


B): Pecos Compressor Station

    	 In order to make this interconnect bi-directional we also need to make the station ( two-compressor units) bi-directional.
	
Scope: Install outlet from Lonestar I/C to inlet filter with 12" piping& valves. Unit discharge would be modified to
tie in to West Texas-20"
	
Cost for material& labor= $ 330,000.
	
If you need more accurate costs ( B -release) please let me know .

	Total cost estimate for this project = $ 533,000.
	